Parents and Community of 27J,
School District 27J continues to work expeditiously to complete 8 construction projects around the School District. Please continue reading for individual project updates and photos.
Brantner Elementary:
- Building under construction: Tilt-up Panels (concrete walls / forms) erected
- Request for Quotation / Request for Procurement of classroom furniture
High School # 3:
- Design development documents at 100% to be complete by first week of April
- Design review meetings with district staff continue
- Working on oil well decommissioning
- Annexation process with City of Thornton continues
Elementary School # 12:
- Design development documents are complete
- General contractor has been selected - FCI Constructors
- FCI working with architect on construction cost estimate
- Coordination conversations with Reunion Metro District
- Open House - April 25th 5:30 to 7:30 pm at Reunion Rec Center
Brighton Heritage Academy:
- Architect firm has been selected - Yon Tanner Architects
- 50% construction drawings completed
- Bid documents ready to hire abatement subcontractor by mid-March
- Initial meeting with Colorado Historical Society and Brighton Historic District once architect firm has been selected
- Meeting with window consultant and installers to discuss lead times
- Request for Quotation / Request for Procurement issued for selection of a general contractor
Additional detailed updates can be found on School District 27J's website.