School District 27J Construction Update: March 21, 2016

Parents and Community of 27J,

School District 27J continues to work expeditiously to complete 8 construction projects around the School District.  Please continue reading for individual project updates and photos.

Brantner Elementary:

  • Building under construction: Tilt-up Panels (concrete walls / forms) erected
  • Request for Quotation / Request for Procurement of classroom furniture

High School # 3:

  • Design development documents at 100% to be complete by first week of April
  • Design review meetings with district staff continue
  • Working on oil well decommissioning
  • Annexation process with City of Thornton continues

Elementary School # 12:

  • Design development documents are complete
  • General contractor has been selected - FCI Constructors
  • FCI working with architect on construction cost estimate
  • Coordination conversations with Reunion Metro District
  • Open House - April 25th 5:30 to 7:30 pm at Reunion Rec Center

Brighton Heritage Academy:

  • Architect firm has been selected - Yon Tanner Architects
  • 50% construction drawings completed
  • Bid documents ready to hire abatement subcontractor by mid-March
  • Initial meeting with Colorado Historical Society and Brighton Historic District once architect firm has been selected
  • Meeting with window consultant and installers to discuss lead times
  • Request for Quotation / Request for Procurement issued for selection of a general contractor

Additional detailed updates can be found on School District 27J's website.